Bristolian Build Up dateThe Bristolian build is gaining momentum as Christmas inches closer. Yachting Developments Team is on a mission with some big goals ahead of them. Just to mention a few of the recent projects; - The captive reel winches have been fitted. - Salon deck-head & dash board construction underway - Robinson Marine Interiors are fitting out the cabinetry work in the Salon. - Teak decks will commence laying in December and target for completion is 28th January 08. - Bimini construction has commenced. - Deck house is being prepped for proof coating. - Southern Spars HM carbon mast & boom is painted and EC6 Carbon side rigging is in production. I will be back to you with my next up date shortly.
|